Penang water cut: Valve replacement work done, supply being restored
Works to replace two 1.2m control valve units which are leaking at the Sungai Dua water treatment plant near George Town, water works and preventive maintenance projects at 22 other locations were fully completed last night.
Penang Water Supply Corporation (PBAPP) chief executive officer K. Pathmanantan said all the water works planned at the Sungai Dua plant and 22 other locations were ahead of schedule, with supply being restored from 11pm last night.
“Water supply is being...
Works to replace two 1.2m control valve units which are leaking at the Sungai Dua water treatment plant near George Town, water works and preventive maintenance projects at 22 other locations were fully completed last night.
Penang Water Supply Corporation (PBAPP) chief executive officer K Pathmanathan said all the water works planned at the Sungai Dua plant and 22 other locations were ahead of schedule, with supply being restored from 11pm yesterday.
“Water supply is being normalised in stages today for 197,025 consumers, which is 33 percent of the 590,000 affected users in Seberang Perai. Stage one needs to be completed by 6am tomorrow as scheduled.
“Level one restoration is not affected by the incident in Sungai Perai because the Sungai Dua plant is pumping water to level one restoration users through other main pipelines,” he said in a statement today.
He said stage two is expected to be implemented starting at 6.01am tomorrow. PBAPP aims to normalise water supply to 495,065 consumers, which is 84 percent of the 590,000 affected users in Seberang Perai and parts of the island.
Pathmanathan said the success of stage two as scheduled, depended on restarting the operation of the damaged section of Sungai Perai underwater pipeline.
Emergency repair works
He said PBAPP is working hard to complete the emergency repair works at Sungai Perai today and will continue to provide updates on the progress of the work.
“Work is being carried out in Sungai Perai after it was delayed last night due to a technical problem where one of the clamps specially designed to be placed over the 1.35m long hole on the pipeline could not be properly installed,” he said.
He said the diving operation was suspended and a heavy crane was brought in and used to lift the unsuitable clamp for on-site modifications.
“This is the fastest engineering solution with the lowest risk of long delays and commercial diving teams are scheduled to lock the modified clamps in place on the damaged pipeline today,” he said.
Earlier, PBAPP announced that approximately 590,000 consumers, including non-domestic ones, will experience scheduled water disruption for 96 hours from 6am yesterday until 6am on Jan 14 to allow for the replacement of two valve units at the Sungai Dua plant as well as other ancillary work at 22 locations throughout Penang.
PBAPP expects at least 101 areas in Seberang Perai Utara and Seberang Perai Tengah to receive water supply after 48 hours.
A total of 157 areas covering Seberang Perai Tengah, Seberang Perai Selatan as well as Northeast and Southwest districts on the island will start receiving water supply after 72 hours.